TUNNEL HOME WATER SYSTEM HOME COBB COUNTY HOME PAGE
Blasting Notices
Easement FAQs
Technical FAQs
Project Map
Sweetwater Construction Site
South Cobb Construction Site
Pump Station Construction Site
Links
 

Contacts

David Rendini
Construction Manager
Parsons Water & Infrastructure
South Cobb Tunnel Project
160 Maxham Road
Austell,GA 30168
770-941-3463

david.rendini@parsons.com

Judy B. Jones, P.E.
Engineering & Records
Division Manager
Cobb County Water System
860 South Cobb Drive
Marietta, GA 30060
770-419-6339

jbjones@cobbcounty.org

 
 
 
 
 

South Cobb Construction Site

The South Cobb Construction Site is located next to the Influent Pump Station site along Lee industrial road. This site is for a construction shaft to allow removal of the main Tunnel Boring Machine (TBM). A smaller tunnel will be driven from here to pick up flows from the Nickajack Creek area. This shaft will take these flows and bring them to the Influent Pump Station, where they will be pumped into the headworks of the South Cobb Water Reclamation Facility.

For a larger image click on the photos below. Hit the return button to return to this page when you are finished looking at the larger image.

Click to view larger image
South Cobb Shaft

South Cobb Construction Site

The South Cobb Shaft is 44 feet in diameter, and is partially excavated through soil. Currently, it is at an elevation to allow a subcontractor to install an 48" diameter odor control pipe which will connect to the odor control facility at the Influent Pump Station.

Click to view larger image

 

Just as the shaft was down to the hard rock, a small tunnel boring unit was used to excavate a small tunnel for an odor control pipe. This pipe will be used to remove odors and gasses from the completed tunnel.

Click to view larger image
SBU preparing to excavate odor control tunnel from SCS to Pump Station, 2009-04-02

Back to top

 

©2008 COBB COUNTY GOVERNMENT   •    COBB COUNTY...EXPECT THE BEST   •   PRIVACY STATEMENT