Sweetwater Construction Site
The Sweetwater site is located on the north west end of the project, and is the site for the Sweetwater Construction Shaft. This is where the TBM is being assembled which will be used to excavate 5-1/2 mile long, 27-foot diameter, tunnel to the South Cobb Water Reclamation Facility, locater on Lee Industrial Boulevard.
The site is in between Maxham and Cardell roads and Timothy Lane. Access to the site is off Maxham Road.
To view the TBM webpage, Click here.
 Sweetwater Shaft Site
Sweetwater Construction Shaft
The Sweetwater Construction Shaft is 280 feet deep, and 40 feet in finished diameter. Initially, it was sunk through weathered rock by excavating with a trackhoe, but transitioned to hard rock and has to be blasted to advance it.
At the bottom of this shaft, the Starter and Tail tunnels were excavated to make room to assemble the Tunnel Boring Machine.
 2009-02-25 SWS Loading the tail tunnel to turn under beneath the
shaft
 This is what the starter tunnel looked like 03-20-09
To view the TBM webpage, Click here.